Why Del Sur's Common Areas Went Thirsty This Year, and Where the Water Went

"About 90 days without water to date."

That line closes the outage log in the Del Sur Community Association's September 4, 2026 newsletter, under a list of 16 separate shutdowns that started November 19, 2025. The water in question is the City of San Diego's recycled water, which runs the irrigation for Del Sur's community-maintained turf, parks and planters. In its August 28 letter to residents, the Board said it recognizes that many areas are "showing signs of stress because of the inconsistent water supply."

The HOA traces those interruptions to the startup of Pure Water San Diego, the City's new drinking-water program. Del Sur's thirsty common areas are a side effect of the City bringing its next water source online.

One Plant, Two Jobs

The City runs the North City Water Reclamation Plant, which treats wastewater to a standard approved for irrigation and other non-drinking uses. According to the HOA, the community's supply has been interrupted since January 2026 by "the City of San Diego's ongoing commissioning and system connection work for Phase 1 of the San Diego Pure Water Program."

The connection between the two systems is built into the plant. On its North City expansion page, the City says it is enlarging the plant from 30 to 52 million gallons per day. That extra capacity is meant to let the plant keep serving its existing recycled-water customers while also supplying the new Pure Water facility.

Until Pure Water is running normally, both demands draw on one supply. The City's October 5 shutdown notice spells it out. Testing the Pure Water connection "requires a significant amount of recycled water." Less water then enters the existing system, which can't hold normal pressure, and the interruption "will affect all customers served by the North City Water Reclamation Plant." The City's scheduled North City shutdown from August 28 to September 5 appears on Del Sur's outage log with the same dates.

Eleven Months of Shutdowns, by the Calendar

The HOA's log shows how uneven the outages have been. A few points from it, plus the City's notices since:

  1. The first outage ran November 19 to 24, 2025, followed by two more in December, one of them running December 19 to 26, through Christmas.
  2. The longest stretch ran 11 days, May 12 to 23, 2026.
  3. The June shutdown began two days earlier than posted, according to the HOA log.
  4. Late summer brought an 8-day outage from July 19 to 27, then a scheduled plant shutdown from August 28 to September 5. Before that one started, the City's August 27 status update warned that service "may have intermittent availability through the end of September as the Pure Water project moves towards startup."
  5. Late September brought a shutdown the City scheduled for September 26 to 29, then extended to October 1 in a September 29 update.
  6. Mid-October brought another North City shutdown, October 12 to 16. On October 16 the City said the work had finished on schedule and the system "is now operational."

The HOA's "about 90 days" count stops at the September 5 restart. The two shutdowns since then come on top of it.

The September shutdown is also the most direct test of the City's August advice. The City asked customers who could stagger irrigation, or switch to potable water, to do so, which would help the system manage daily demand swings and keep availability more consistent. For a community whose common areas are irrigated by recycled water, that request describes how little room for error the system has right now.

What Happens on the Ground When the Pipe Goes Dry

Del Sur's maintenance contractor is BrightView. According to the August 28 letter, crews decide where to water first based on each area's condition, plant material, visibility and water needs. When recycled water is flowing, they make the most of each window with efficient cycles and deep watering. During shutdowns they bring in water trucks and deep-water the priority areas to hold soil moisture and protect the plantings most at risk.

So a struggling patch of turf next to a healthy planter usually reflects triage, and it doesn't mean someone forgot. The letter also covers fertilizer:

"Please be assured that no fertilizing or extra soil treatment is needed on your end. The landscape project manager has already integrated targeted fertilization and routine soil maintenance directly into our community-wide landscape recovery action plan."

Your own front yard runs on a different pipe. The HOA says front-yard household irrigation runs on "the independent potable water grid and is entirely unaffected." That explains a pattern you can see on almost any Del Sur street this year: green lawns at the houses, tired turf on the shared strips between them.

The steep open-space slopes get a different kind of attention. The Association's herd from Good Shepherds finished its work in Cerro Del Sur and moved to the open space near Del Sur Elementary School. The September 4 newsletter says the program cleared 8.026 acres across three common-area parcels. Walking trails next to the grazing slopes have reopened, though trails in the area marked blue on the newsletter's map stayed closed, and temporary electric fencing goes up wherever the goats are working. Good Shepherds has a Del Sur page for questions about the animals.

October Added a Second, Unrelated Problem

Not every recycled-water outage this fall traces back to Pure Water. In an October 6 notice, the City said the Canyonside Pump Station, which helps supply recycled water, "is currently not working." The outage affects everyone who gets recycled water from that pump station and from Black Mountain Reservoir. The affected area is listed as the San Dieguito 825 and San Dieguito 600 Pressure Zone. The start date is October 5, 2026, and the completion date is "TBD."

That notice names pressure zones, not neighborhoods, so it doesn't settle which streets are affected. What it does show is that the recycled-water network has failure points beyond the North City plant, and a repair with no end date can stack on top of a scheduled Pure Water shutdown.

When the Water Is Supposed to Settle Down

The City's recycled water page says temporary impacts are expected while it prepares for "the commissioning and startup of Phase 1 of Pure Water San Diego... through 2026." The page now posts every notice sent to recycled-water customers, newest first, so anyone can check for a scheduled shutdown before the HOA mentions it.

The City's 2026 Pure Water presentation describes Phase 1 as more than 90 percent complete, with commissioning starting in summer and the first purified water expected to reach Miramar Reservoir by the end of 2026. It targets full operation at 30 million gallons per day in 2027. The City's May 2026 FAQ is more gradual. It expects initial production of about 7.5 million gallons per day, rising to 30 once the Morena Pump Station comes online, which it says will likely be about a year after launch. All of these are City targets. The October notices still describe connection testing, not deliveries.

The HOA's outlook follows the same timeline. The City has said the periodic shutdowns should last through the end of the year, and the Board wrote that it is "highly optimistic that 2027 will bring a stable, uninterrupted water supply," so turf, parks and planters can recover fully.

Each restart comes with its own issues. The City warns that once service returns, customers may see air in the lines and swings in pressure, and it recommends checking recycled-water irrigation systems and releasing trapped air before going back to normal operation. After the September restart, the HOA asked residents to report any breakages or sprinklers that seem to be overwatering. The Ranch House office at 15455 Paseo Del Sur takes those reports at 858-759-1921, Monday through Friday, 8 a.m. to 4:30 p.m.

At Shay Realtors, we keep track of the things that shape day-to-day life in Del Sur, from City water schedules to what's happening on the open-space slopes. If you'd like a local's read on how this year's common-area conditions fit the bigger picture for your street, talk to a local expert and schedule your free neighborhood consultation.